(06/16/2018)
There are no projects in Calhoun County funded directly from the Road Bond Levy passed by WV voters, according to J. Rusty Roten, District Engineer/Manager, WVDOT, Division of Highways.

Roten said the road bond was for large projects such as US 33, Scott Miller Hill in Roane County,the WV 2 Widening in Wood and other major projects.

Funded projects for Calhoun 2018:

Stinson Road Resurfacing – CR 17, Milepost 0.00 to 1.55

Back Fork Resurfacing – CR 4, Milepost 7.04 to 9.01

Milo Road Resurfacing – CR 13, Milepost 0.00 to 2.56

Little White Oak Resurfacing – CR 15/2, Milepost 4.12 to 5.54

Russet Road Resurfacing, CR 7, Milepost 1.73 to 5.23

Arnoldsburg Rd Slip Repair – US 33, Milepost 6.34

Projects #1 through #4 are DMV Fee projects pay by revenues generated from the increase in DMV Fees, luxury taxes, gas tax, etc. Project #5 is a state funded paving project from the yearly paving program fund.

Project #6 is a state funded slip repair project from the yearly slip repair fund.

The Back Fork and Milo Road projects are likely completed.

The Stinson Road resurfacing started this week.


Hur Herald ®from Sunny Cal
The information on these pages, to the extent the law allows, remains the exclusive property of Bob Weaver and The Hur Herald. information cannot be not be used in any type of commercial endeavor, or used on a web site without the express permission of the owner. ©Hur Herald Publishing, 1999, 2000, 2001, 2002, 2003, 2004, 2005, 2006, 2007, 2008, 2009, 2010, 2011, 2012, 2013, 2014, 2015, 2016, 2017, 2018