(04/14/2011)
The U.S. Army Corps of Engineers has reopened Burnsville Lake to boat traffic.

Repairs have been made to a damaged waterline.

Construction is also underway to enhance the structural stability of three Burnsville Lake tainter gates located on the top of the dam.

A repair crew began working on the structure on April 4. The work is expected to take approximately 6 weeks to complete, and the crew will be working weekdays from 7 a.m. to 5 p.m.

During that time no one will be allowed to cross the top of the dam for safety reasons. Once repairs are complete, the dam will be opened to pedestrian traffic.


Hur Herald ©from Sunny Cal
The information on these pages, to the extent the law allows, remains the exclusive property of Bob Weaver and The Hur Herald. information cannot be not be used in any type of commercial endeavor, or used on a web site without the express permission of the owner. Hur Herald published printed editions 1996-1999, Online ©Hur Herald Publishing, 1999, 2000, 2001, 2002, 2003, 2004, 2005, 2006, 2007, 2008, 2009, 2010, 2011, 2012, 2013, 2014, 2015, 2016, 2017, 2018, 2019