Route 5 travelers will be happy to know the new Elizabeth bridge will be opened for traffic on Monday, according to George Shinksy, District Three construction engineer.

"Assuming no last minute problems arise, we expect to divert traffic from the temporary bridge onto the new structure around noon on Monday," he said.

Shinsky said the project is coming in before the estimated date of completion of August 31.

"Every project has some unexpected problems, but for the most part, this project went fairly well," Shinsky added. The project was marred by a worker falling to his death during the construction of the temporary bridge.

Orders Construction of St. Albans is the contractor for the $3.8 million dollar structure, which started in January, 2000.


Hur Herald ©from Sunny Cal
The information on these pages, to the extent the law allows, remains the exclusive property of Bob Weaver and The Hur Herald. information cannot be not be used in any type of commercial endeavor, or used on a web site without the express permission of the owner. Hur Herald published printed editions 1996-1999, Online ©Hur Herald Publishing, 1999, 2000, 2001, 2002, 2003, 2004, 2005, 2006, 2007, 2008, 2009, 2010, 2011, 2012, 2013, 2014, 2015, 2016, 2017, 2018, 2019